May saw the following projects drop off my list:
De Novo (originally anticipated June of '18) has been the oldest non-Natalia Silva project on my list for quite some time, but no more! The decks and coin arrived in May, looking mighty fine. Likewise, Arabesque (August '18) had previously been the second oldest non-apparently-dead project on my list (because in addition to the two Natalia Silva projects on my list, the Sun Tzu project appears to be dead as the project creator disappeared about a year ago), and it, too, has joined the ranks of successfully delivered. This marks the first time in... years?... that I haven't been anticipating the delivery of a Lotrek project. (That's going to change tomorrow morning, alas.) More recent projects, the Pride of Peacocks (April '19) and Golden Spike 150th Anniversary (April '19) came in very close to their originally projected arrival time, and Cyberpunk (May '19) arrived on time... although, some of the decks will be re-sent once they are re-printed, after a printing error was discovered to have escaped the production line. I'm removing it from the list for the time being, even though it's fair to say the project isn't *quiiite* a hunder percent fulfilled.
Also arriving in May, before it could even be added to the list, was a Motley Pack -- Transformation Playing Cards, which was originally anticipated in July of this year. Way to go, Sunish! Recall, too, that Albino Dragon shipped the Gorilla Deck, Silverback Edition, in mid-April, also long before it would have been added to the list (for June).
Thus, five projects drop off the list in May, and two fall off before they could even be added. Not too shabby. Meanwhile, one project gets added this month!
Here's the list of playing card-related projects that have had an anticipated delivery of up-to and including June, 2019 for which I am awaiting fulfillment:
- Muertos (January '18) -- No word since Halloween 2018, saying this project is still in work. Radio silence since then.
- Avalon (May '18) -- See above.
- Sun Tzu (July '18) -- No word since an update posted in late May '18.
- Vegas Diffractor (March '19) -- Filipe let backers know that production issues have delayed the process by four months, so fulfillment is now anticipated in July. An update from just a couple weeks ago confirmed that is still the target.
- Hello Tiki V2 (April '19) -- Surveys have been sent out, and it appears that shipment is still slated for sometime in June, as Montenzi has been suggesting for a couple months now. I've received some samples in the mail and they are simply OFF THE HOOK.
- Agenda Redux (May '19) -- As of May 30th, fulfillment is poised to commence *immediately.* However, if backers selected to have this project ship with Facade...
- Agenda Facade (May '19) -- As of earlier today (June 3rd), electronic proofs are pending approval, and then physical production can get queued up. Deliveries that were to be combined with Agenda Redux will cause some delay, as a result. Currently looking to be about six weeks out.
- Samedi - Voodoo (May '19) -- As of last month, a slip in the production queue looks to be delaying completion and fulfillment by a few weeks, into June. Recent comments indicate that they are still on target for around the third week of June.
- Beta ONE (June '19) -- Surveys have been sent out, and there is no indication that they will miss their June projected fulfillment time frame.
And you? What deliveries are you currently anticipating from non-retail outlets?